Crossovers, possession windows and works bundling

Impact of the policy to remove track equipment on construction schedules and maintenance costs.

Client
INFRABEL
Location
Belgium
Date
2013/2014
Crossovers, possession windows and works bundling triangle
cible

Context and objectives

Infrabel is pursuing a policy of reducing the number of switches and crossings. Within this framework, the assignment was to establish the economic case for removing bi-directional signalling crossovers (known as IPCS in French railway terminology), weighed against operational robustness and maintenance economics, and in particular the bundling of maintenance works.

cible

Approach and results

The approach comprised four strands:

  • Modelling and simulating the maintainer’s organisation
  • Modelling and simulating maintenance economics (progress rates, unit costs)
  • Simulating the effects on operational robustness
  • Establishing the overall economic equation on a probabilistic basis
Is your organisation facing any of these situations?
Contact usarrow
Switzerland
6, rue des Deux-Gares
CP 553
1800 Vevey
France
11, rue de Paradis
75010 Paris
Portugal
SWI2M – IT company of IMDM,
Startup Madeira,
C. da Penteada, freguesia de São Roque
9020-105 Funchal
© 2026 IMDM | powered by tokiwi
linkedin
to top