Load calculation for the electrical grid

Calculate the flow of loads in the grid following the construction of new substations.

Client
SEVJ
Location
L'Orient, Switzerland
Date
2021/2022
Load calculation for the electrical grid triangle
cible

Context and objectives

The assignment set out to determine line currents and node voltages following the construction of several substations and the addition of large consumers.

The objectives included:

  • Developing the long-term asset strategy for the network
  • Analysing different contractual options for renewing and maintaining the network
  • Estimating the marginal cost of energy performance at renewal
cible

Approach and results

The approach was based on modelling the electrical grid in NEPLAN, with the following steps:

  • Model the network
  • Collect and analyse a full year of network measurements
  • Calculate loads
  • Propose the optimal network topology

Tools used

NEPLAN

Is your organisation facing any of these situations?
Contact usarrow
Switzerland
6, rue des Deux-Gares
CP 553
1800 Vevey
France
11, rue de Paradis
75010 Paris
Portugal
SWI2M – IT company of IMDM,
Startup Madeira,
C. da Penteada, freguesia de São Roque
9020-105 Funchal
© 2026 IMDM | powered by tokiwi
linkedin
to top